docs(01-07): track completed preparation and open acceptance gate

This commit is contained in:
UnixNight committed 2026-11-13 16:49:31 -05:00
1 parent 52a3e2d5ff
commit 215d01e43e
3 files changed
+36 -24

No files matched your search

+11 -3
View File
@@ -39,7 +39,7 @@ Integer phases are planned work; decimal phases may be inserted for urgent recov
2. A tester can reproduce identified whole-original reference scenarios from an isolated generated installation and inspect corresponding input/events, images and audio where applicable; unavailable execution keeps this criterion open.
3. A reviewer can trace every full-game capability from original evidence through current implementation, platform receipts, discrepancies and its remaining acceptance condition.
4. Testers can repeat the same baseline movement/route scenarios on native Linux and native Windows with exact revision identities; Wine/cross-publish receipts remain separately labeled and cannot close missing native execution.
**Plans:** 6/7 plans executed
**Plans:** 7/7 autonomous preparation/reconciliation plans recorded; actual 01-07-02 capture/review and Phase 1 acceptance remain pending.
**Wave 1**
- [x] 01-01-PLAN.md
@@ -55,7 +55,15 @@ Integer phases are planned work; decimal phases may be inserted for urgent recov
- [x] 01-06-PLAN.md
**Wave 5** *(blocked on Wave 4 completion)*
- [ ] 01-07-PLAN.md
- [x] 01-07-PLAN.md
Autonomous preparation is complete: 11,000 immutable files pass readiness and
the complete local suite passes in 782.05s. Actual task 01-07-02 capture/review
remains human_needed: 0/120 original/native obligations accepted and ten human
findings pending. All EVID requirements remain Pending; Phase 1 is not accepted.
The primary reviews readiness before one combined session. Retained quota
handoff files are historical until primary consumption; the final SUMMARY
records completed task 3 and pending human dependencies. No Phase 2 advancement.
### Phase 2: Faithful Movement and Scene Handoffs
**Goal:** Players move, contact the world and return from scripts/scenes with the original movement, animation, camera and state ownership intact.
@@ -151,7 +159,7 @@ Execution follows 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8, subject to the ex
| Phase | Plans Complete | Status | Completed |
|-------|----------------|--------|-----------|
| 1. Reproducible Fidelity Baseline | 6/7 | In Progress | - |
| 1. Reproducible Fidelity Baseline | 7/7 preparation | Human acceptance pending (0/120) | - |
| 2. Faithful Movement and Scene Handoffs | 0/TBD | Not started | - |
| 3. Original Actors, Hazards and Combat | 0/TBD | Not started | - |
| 4. Complete Gadget and Vehicle Use | 0/TBD | Not started | - |