docs(01-07): track completed preparation and open acceptance gate

This commit is contained in:
UnixNight committed 2026-11-13 16:49:31 -05:00
1 parent 52a3e2d5ff
commit 215d01e43e
3 files changed
+36 -24

No files matched your search

+11 -3
View File
@@ -39,7 +39,7 @@ Integer phases are planned work; decimal phases may be inserted for urgent recov
2. A tester can reproduce identified whole-original reference scenarios from an isolated generated installation and inspect corresponding input/events, images and audio where applicable; unavailable execution keeps this criterion open.
3. A reviewer can trace every full-game capability from original evidence through current implementation, platform receipts, discrepancies and its remaining acceptance condition.
4. Testers can repeat the same baseline movement/route scenarios on native Linux and native Windows with exact revision identities; Wine/cross-publish receipts remain separately labeled and cannot close missing native execution.
**Plans:** 6/7 plans executed
**Plans:** 7/7 autonomous preparation/reconciliation plans recorded; actual 01-07-02 capture/review and Phase 1 acceptance remain pending.
**Wave 1**
- [x] 01-01-PLAN.md
@@ -55,7 +55,15 @@ Integer phases are planned work; decimal phases may be inserted for urgent recov
- [x] 01-06-PLAN.md
**Wave 5** *(blocked on Wave 4 completion)*
- [ ] 01-07-PLAN.md
- [x] 01-07-PLAN.md
Autonomous preparation is complete: 11,000 immutable files pass readiness and
the complete local suite passes in 782.05s. Actual task 01-07-02 capture/review
remains human_needed: 0/120 original/native obligations accepted and ten human
findings pending. All EVID requirements remain Pending; Phase 1 is not accepted.
The primary reviews readiness before one combined session. Retained quota
handoff files are historical until primary consumption; the final SUMMARY
records completed task 3 and pending human dependencies. No Phase 2 advancement.
### Phase 2: Faithful Movement and Scene Handoffs
**Goal:** Players move, contact the world and return from scripts/scenes with the original movement, animation, camera and state ownership intact.
@@ -151,7 +159,7 @@ Execution follows 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8, subject to the ex
| Phase | Plans Complete | Status | Completed |
|-------|----------------|--------|-----------|
| 1. Reproducible Fidelity Baseline | 6/7 | In Progress | - |
| 1. Reproducible Fidelity Baseline | 7/7 preparation | Human acceptance pending (0/120) | - |
| 2. Faithful Movement and Scene Handoffs | 0/TBD | Not started | - |
| 3. Original Actors, Hazards and Combat | 0/TBD | Not started | - |
| 4. Complete Gadget and Vehicle Use | 0/TBD | Not started | - |
+22 -18
View File
@@ -2,17 +2,17 @@
gsd_state_version: "1.0"
current_phase: 01
current_phase_name: Reproducible Fidelity Baseline
status: executing
stopped_at: Paused by15% quota guard;01-07task3 test/review pending; HANDOFF takes precedence
last_updated: "2026-11-13T17:28:45.982275+00:00"
last_activity: 2026-11-12
last_activity_desc: Phase 01 execution started
state_head: c60248dbfe5c8d151677babca0543af1f1d1b5e0
status: ready_for_verification
stopped_at: Completed 01-07 autonomous preparation; primary readiness review then one combined human session; acceptance OPEN 0/120
last_updated: "2026-11-13T21:48:54.245Z"
last_activity: 2026-11-13
last_activity_desc: 01-07 autonomous preparation verified; actual human acceptance pending 0/120
state_head: 52a3e2d5ff19a87e1bd268cdda8eb0ec6bf5e451
progress:
total_phases: 8
completed_phases: 0
total_plans: 7
completed_plans: 6
completed_plans: 7
percent: 0
---
@@ -27,24 +27,24 @@ See: .planning/PROJECT.md (updated 2026-11-12)
## Current Position
Phase: 01 (Reproducible Fidelity Baseline) — EXECUTING
Phase: 01 (Reproducible Fidelity Baseline) — HUMAN ACCEPTANCE PENDING
Plan: 7 of 7
Status: Interrupted —01-07 task1 complete; task2 human_needed; task3 fullsuite active
Last activity: 2026-11-12 — Phase 01 execution started
Status: Ready for primary review — 7/7 autonomous preparation records; actual 01-07-02 capture/review human_needed, 0/120 accepted. Phase 1 remains open; Phase 2 not advanced.
Last activity: 2026-11-13 — Task 3 committed, complete local suite passed in 782.05s; final summary committed.
Progress: [░░░░░░░░░░] 0%
## Performance Metrics
- Total plans completed: 0
- Average duration: Not established
- Total execution time: 0 hours
- Autonomous preparation plans recorded: 7/7; accepted phases: 0/8
- Average duration: See per-plan metrics; elapsed intervals include pauses
- Total active execution time: Not continuously measured
| Phase | Plans | Total | Avg/Plan |
|-------|-------|-------|----------|
| - | - | - | - |
Recent trend: No execution plans completed in this roadmap. Existing project work predates initialization and retains its documented bounded evidence.
Recent trend: All seven preparation/reconciliation records exist; actual task 01-07-02 and Phase 1/EVID acceptance remain open. Existing project work retains its documented bounded evidence.
**Per-Plan Metrics:**
| Plan | Duration | Tasks | Files |
@@ -55,6 +55,7 @@ Recent trend: No execution plans completed in this roadmap. Existing project wor
| Phase 01 P04 | 16 min | 2 tasks | 5 files |
| Phase 01 P05 | 12h 4min | 2 tasks | 7 files |
| Phase 01 P06 | 14 min | 2 tasks | 4 files |
| Phase 01 P07 | 4h 36min elapsed incl quota pause; suite 782.05s | 2 tasks | 16 files |
## Accumulated Context
@@ -78,13 +79,16 @@ Recent trend: No execution plans completed in this roadmap. Existing project wor
- [Phase 01]: Runtime package provenance retains actual completed publish source/dirty/diff identity; selected external tools are identified without redistributing executables.
- [Phase 01]: No display and only auto_null audio yields failed native preflight; all forty Linux obligations retain explicit physical/audible capture dependencies.
- [Phase 01]: Linux matrix history revalidates saved receipt hashes and requires new launch/session IDs; focused captures cannot replace continuous route lifetimes.
- [Phase 01]: Ready materials and local regressions never substitute for actual original/native acceptance; all 120 obligations and ten named human findings remain open.
- [Phase 01]: The integration agent reconciles returned collector records through specified artifact mappings; the tester collects, observes and returns one combined session.
### Pending Todos
None captured separately. Next action: `$gsd-discuss-phase 1` or `$gsd-plan-phase 1`.
Primary readiness review of final 01-07 source/materials, then the single combined human session in docs/evidence/checkpoint-session.md. All EVID requirements remain Pending. Do not launch Phase 2 from preparation counts.
### Blockers/Concerns
- Final 01-07 readiness passes 11,000 immutable files and local suite passes; strict audit still exits 1 with no structural errors, 0/120 accepted obligations and ten pending human findings. This is an actual evidence dependency, not a test failure or auto-approval gate.
- Phase 1: Working whole-original reference capture and current native Windows comparison remain unverified access dependencies. Record limitations; keep acceptance open while independent source-backed recovery continues.
- Phase 2: Real derived responses, helper membership/activation/cleanup, physical order and shared mutable reclip remain live admission gates. Lab/outside capsule stays until its replacement gate closes.
- Full-game completion requires current integrated native Linux/Windows and original-reference evidence. Compilation, copied-original probes and Wine have narrower scopes.
@@ -104,6 +108,6 @@ No original-required category deferred outside full reconstruction. Later phases
## Session Continuity
Last session: 2026-11-13T17:04:40.619Z
Stopped at: Paused by15% quota guard;01-07task3 test/review pending
Resume file: .planning/phases/01-reproducible-fidelity-baseline/HANDOFF.md
Last session: 2026-11-13T21:48:54.215Z
Stopped at: Completed 01-07 autonomous preparation; primary readiness review then one combined human session; acceptance OPEN 0/120
Resume file: None
+3 -3
View File
@@ -46,8 +46,8 @@
],
"next": {
"command": "$gsd-progress --next",
"label": "Advance to the next step",
"reason": "Phase 1 of 8 · 0% · executing"
"label": "Review prepared Phase 1 checkpoint and pending combined human session",
"reason": "Phase 1 remains open: 7/7 autonomous preparation records, actual acceptance human_needed 0/120; Phase 2 not advanced"
},
"updated_at": "2026-11-13T17:04:38.735Z"
"updated_at": "2026-11-13T21:49:00Z"
}